Verbatim: Street resurfacing schedule announced

The city of Fort Wayne's Traffic Engineering Department issued this statement today:

Please be advised the following is the schedule of streets to be resurfaced:

  • State Blvd. – Anthony to Florida – August 1, 2012 Binder
  • Vance Ave. – Reed to Delray August 1, 2012 Binder
  • Crescent Ave. – State to Lynn August 1, 2012 Binder
  • State Blvd. – St. Joe to Kentucky August 3, 2012 Surface
  • Vance Ave. – Reed to Delray August 3, 2012 Surface
  • Crescent Ave. – State to Lynn August 3, 2012 Surface
  • State Blvd. - Anthony to Florida August 6, 2012 Surface
  • Sherman Blvd. – State to Goshen August 6, 2012 Surface
The above schedule is dependent on weather conditions.

The contractor, E & B Paving Inc., will be resurfacing the above streets. Two-way traffic will be maintained at all time.

The contractor will be responsible for placement and maintenance of all warning signs and barricades.

For further information or for problems that may develop contact the Traffic Engineering Department at 427-1172.