You choose, we deliver
If you are interested in this story, you might be interested in others from The Journal Gazette. Go to www.journalgazette.net/newsletter and pick the subjects you care most about. We'll deliver your customized daily news report at 3 a.m. Fort Wayne time, right to your email.

Schools

  • IU, Purdue execs to begin meeting on IPFWs future
    Indiana University and Purdue University have agreed to begin meeting to discuss options for the future management of IPFW, which currently is managed by Purdue.
  • Marching bands
    Northrop, East Noble, Bishop Dwenger, Concordia, Adams Central and Heritage took home honors Saturday following a high school marching band contest at DeKalb High School.
  • Northcrest students get vision tests
    Nearly 200 first-, third- and fifth-graders at Northcrest Elementary got their eyes checked with the flash of a laser wand Wednesday.
Advertisement

FWCS board OKs loan for $119 million build project

– The Fort Wayne Community Schools board Monday authorized the district to begin the process to borrow money for its voter-approved, $119 million building project.

The $7 million in bonds authorized Monday is the smallest in the series, said FWCS Chief Financial Officer Kathy Friend. The money will be used for introductory costs such as architect and design fees, site preparation, bid documents, consultant and advisor fees and financing.

Because of the scope of the project, it will take the district three or four years to spend the $119 million, Friend said. The bonds will be taken out as needed so the district isn’t paying interest on money not immediately required for construction, she said.

The $119 million project will address repairs and renovations at 36 of the district’s buildings in most need of upgrades on masonry, windows, heating and cooling systems and flooring. In 2013, the district will begin its major projects at Harrison Hill Elementary, Memorial Park Middle and Snider High schools.

The district will pay off this first series of bonds through tax increases in 2013 and 2014. Friend said the district will be diligent in making sure it doesn’t increase taxes any higher than it promised in the ballot question voters approved in the spring, to add $27 per year for a $100,000 home.

The board’s authorization to borrow money also required a public hearing, which was held within the regular board meeting. No one from the public came forward to speak during that designated time.

The next step in the process is a common wage hearing, scheduled for today. The hearing will set a minimum wage for positions associated with construction projects. Other units of government will participate also, Friend said.